Shell Europa (2019)

C-Innovation vessels Island Venture, Island Performer, Carol and Fast Hauler were brought to the Europa Pipeline where a Phase 2 completion took place.

Pipeline communication was achieved to the Mars platform following four tractor runs:

  • Run #1 – 14,500’
  • Run #2 – 26,980’ (world tractor distance!)
  • Run #3 – 22,000’
  • Run #4 – 26,038’

The C-Innovation team was successfully able to flush out the pipeline to seawater, enabling riser cut and abandonment, which will undoubtedly occur in the future.